our Projects

Projects’ Description, Positions Held and Tasks Performed

Hydropower and Civil Construction Expert Project: Muzizi HPP is a run‐of‐river high head (450 m) peaking plant

Project: Isimba HPP, costing USD 567 million, is mainly comprised of spillways, gravity structures 

Project: Tarbela Dam in terms of fill volume is comprised of 149 million m3  and is 143 m high

Project:  Karuma  HPP,  costing  USD  1.7  billion,  comprises a  dam,  power intake,  large underground 

Project: Patrind Hydropower Project is a 150 MW (647 GWh) run of the river project involving inter 

Project: The Ilisu HPP with 1,200 MW installed capacity located on Tigris River in Eastern Turkey,  involved 

This World Bank-funded project comprised rehabilitation of Yntumak reservoir re-equipment works on the Nura River included a 1.6km long

The Tanger Med 2 port includes 4.8 km of dikes, a basin with an area of 160 hectares of earth platform formed

Project: Karura Hydropower Development Plant with 55 MW is a run-of-river scheme

Project: Lotsane dam involved the construction of a 30 m high water supply dam on a deeply weathered

: The project involved construction of 75 m high rockfill dam with central

The Seymareh HEPP involved construction of 180 m high thin arch dam 

The project components are comprised of a 91 m high RCC dam located

Kárahnjúkar Hydroelectric Project is located in Eastern Iceland

This project consists of a 180 m high zoned rockfill dam, integrated

Gomal Zam Dam Project involved the construction of a 133

Wala Dam project involved the construction of a 52 m high Dam with a central

This high head (2,000 m) hydropower development involved three

This project consists of a 165 m high zoned rockfill dam and an underground

The Berke Dam and Hydroelectric Project, located in Eastern Turkey

Mafeteng Dam, a homogeneous earthfill dam, constructed with partially

A feasibility study funded by the French Government and the EEC involved 

The scheme involved a storage dam on the Metsemotlhaba River

FAO funded a multi-disciplinary feasibility study including an 80m

Project: Ain Zada dam is a 50 m high and 940 m long rockfill dam with a fill volume of 2.6 million

Project: Tarbela Dam in terms of fill volume is comprised of 149 million m3 and is 143 m high with a crest length of 2,743 m plus an axillary dam. It has two spillways, 

Project: Lar dam is a 105 m high composite earth and rockfill dam with a crest length of 1,500 m and fill volume of 13 million m3

Kárahnjúkar Hydroelectric Project is located in Eastern Iceland on glacier fed rivers Jökulsá á Dal and Jökulsá í Fljótsdal.